Case study · Fit-out · AMPM Building Services + Gemini AMPM

One landlord deadline.
Three compliance regimes.

M&E, fire detection, compartmentation and security delivered as one workstream — so the move-in date didn't slip behind the regulator.

Financial-services client · Mayfair 18,000 sq ft · 14 weeks · move-in on the contracted date

The brief

A financial-services firm taking 18,000 sq ft of newly-vacated Cat-A space in Mayfair, with a hard move-in date dictated by the lease structure. The landlord had handed back Cat-A shell; the firm needed Cat-B fit-out completed, life-safety-compliant, and signed off by the building's responsible person — in 14 weeks.

What looked like a standard fit-out had three regulators under it: BSA-grade compartmentation through the demising walls, fire detection integrating with the landlord's addressable system, and security scoped against the firm's group IT standard. Three trades, three sign-off paths, one calendar.

The approach — one delivery partner, one project clock

01 · Survey + design freeze (2 weeks)

Existing compartmentation surveyed against the as-builts; gaps and disagreements documented before any trade started. M&E design frozen against the IT brief and the landlord's chiller capacity. Nothing went on order until the survey-and-design pack was signed by all three sign-off chains.

02 · M&E first-fix + compartmentation (6 weeks)

Power, lighting, comms containment, chilled-water taps and HVAC ductwork first-fix; compartmentation in parallel — they share the demising walls. Procore tracked as-built deviations daily, so the second-fix and life-safety teams worked off a live drawing pack.

03 · Detection + security commissioning (4 weeks)

Fire-detection devices installed, addressed and commissioned against the landlord's panel; security cabling, access-control readers and CCTV commissioned against the firm's IAM standard. Both witnessed and signed off in the same week.

04 · Cat-B finishes + handover (2 weeks)

Joinery, finishes, furniture, snagging. The compliance pack — as-builts, certificates, asset register — handed over on move-in day, not six weeks after.

"We could have done this with three contractors and a project manager glueing them together. The fact we didn't is why we hit the date."

Head of UK Estates, client

The outcome

Occupation on the lease-stipulated date, with the drawing pack, certificate set and asset register handed over the same morning. The responsible person accepted the integrated commissioning on first witness. No remedials, no extensions, no holdover.

14 WKS
survey kick-off to move-in
18,000
sq ft, Cat-A to Cat-B
3
regulators sequenced in one programme
0
days lost to compliance sign-off
  • Project team: AMPM Building Services (M&E, fit-out) · Gemini AMPM (passive fire, fire detection)
  • Frameworks: Building Safety Act 2022 · BS 5839 · BS 7273
  • Operating stack: Uptick · Procore · M365 SharePoint